Flint River Outfall Replacement Phase 2
This project was a dig and replace project that consisted of laying 11,752 LF of 42", 48" & 60" fiberglass reinforced polymer gravity sewer pipe in an existing sewer easement...
Completion
100%
Hopkins Creek Interceptor Project
This project consisted of the installation of a new gravity sewer line in wet and rocky conditions. Nearly the entire length of the line was drilled and blasted in order...
Completion
100%
GDOT I-285/SR 400 Interchange Improvement Project – Trenchless Crossings
This project consisted of jack and bore 510 L.F. 72’’O.D. Steel Casing for 54’’ RCP Storm Drain (Robbins SBU-M), jack and bore 450 L.F. 30’’ O.D. Steel Casing for new...